If some models are based on a abstract time - only the number of cycles is important - others are based on a real time. In order to manage the time, GAMA provides some tools to manage time.
First, GAMA allows to define the duration of a simulation step. It provides access to different time variables. At last, since GAMA 1.7, it provides a date variable type and some global variables allowing to use a real calendar to manage time.
GAMA provides three important global variables to manage time:
- cycle (int - not modifiable): the current simulation step - this variable is incremented by 1 at each simulation step
- step (float - can be modified): the duration of a simulation step (in seconds). By default the duration is one second.
- time (float - not modifiable): the current time spent since the beginning of the simulation - this variable is computed at each simulation step by: time = cycle * step.
The value of the cycle and time variables are shown in the top left (green rectangle) of the simulation interface. Clicking on the green rectangle allows to display either the number cycles or the time variable. Concerning this variable, it is presented following a years - month - days - hours - minutes - seconds format. In this presentation, every months are considered as being composed of 30 days (the different number of days of months are not taken into account).
Concerning the step facet, the variable can be modified by the modeler. A classic way of doing it consists in reediting the variable in the global section:
global { float step <- 1 #hour; }
In this example, each simulation step will represent 1 hour. This time will be taken into account for all actions based on time (e.g. moving actions).
Note that the value of the step variable should be given in seconds. To facilitate the definition of the step value and of all expressions based on time, GAMA provides different built-in constant variable accessible with the "#" symbol :
-
#s : second
-
#s : second init { //GAMA provides different values for temporal unities - these values are given in seconds write "1#s: " + 1#s; write "1#mn: " + 1#mn; write "1#hour: " + 1#hour; write "1#day: " + 1#day; write "1#month: " + 1#month; write "1#year: " + 1#year;
//Note that these values are constant: the value #month is always equal to 30 #day.
} reflex info_time { write "\n-------------------------------------------"; //the global variable cycle gives the current step of the simulation write "cycle: " + cycle;
//the global variable time gives the current duration (in seconds) since the beginning of the simulation: time = cycle * step //The value of the time facet can be seen - in a date-time presentation - in the top-left green info panel (click on the number of cycle to see the time value). //When presenting the time value, a month is considered as being composed of 30 days. For a more realistic calendar, use the starting_date global value (see the Date type and Real dates model) write "time: " + time;
} }
//definition of the date of begining of the simulation - defining this date will allows to change the normal date management of the simulation by a more realistic one (using calendar) date starting_date <- date([2011,1,2,1,1,30]);
//be careful, when real dates are used, modelers should not use the #month and #year values that are not consistent with them
float step <- 1#h;
init {
write "starting_date: " + starting_date;
//there are several ways to define a date.
//The simplest consists in using a list of int values: [year,month of the year,day of the month, hour of the day, minute of the hour, second of the minute]
date my_date <- date([2010,3,23,17,30,10]); //correspond the 23th of March 2010, at 17:30:10
//It is also possible to define a date through a string:
date my_date2 <- date("2010-3-23T17:30:10+07:00");
write (my_date2);
//it is possible to get the current date by using the "now" string:
date today <- date("now");
write (today);
write "\n ----------------------------------------------- " ;
//GAMA provides several operator to manipulate dates:
//for instance, it is possible to compute the duration in seconds between 2 dates:
float d <- starting_date - my_date;
write "duration between " + my_date + " and " + starting_date + " : " + d + "s";
write "\n ----------------------------------------------- " ;
//to add or substract a duration (in secondes) to a date:
write "my_date2 + 10: " + (my_date2 + 10);
write "my_date2 - 10: " + (my_date2 - 10);
write "\n ----------------------------------------------- " ;
//to add or substract a duration (in years, months, weeks, days, hours, minutes, secondes) to a date:
write "my_date2 add_years 1: " + (my_date2 add_years 1);
write "my_date2 add_months 1: " + (my_date2 add_months 1);
write "my_date2 add_weeks 1: " + (my_date2 add_weeks 1);
write "my_date2 add_days 1: " + (my_date2 add_days 1);
write "my_date2 add_hours 1: " + (my_date2 add_hours 1);
write "my_date2 add_minutes 1: " + (my_date2 add_minutes 1);
write "my_date2 add_seconds 1: " + (my_date2 add_seconds 1);
write "my_date2 substract_years 1: " + (my_date2 substract_years 1);
write "my_date2 substract_months 1: " + (my_date2 substract_months 1);
write "my_date2 substract_weeks 1: " + (my_date2 substract_weeks 1);
write "my_date2 substract_days 1: " + (my_date2 substract_days 1);
write "my_date2 substract_hours 1: " + (my_date2 substract_hours 1);
write "my_date2 substract_minutes 1: " + (my_date2 substract_minutes 1);
write "my_date2 substract_seconds 1: " + (my_date2 substract_seconds 1);
}
reflex info_date {
//at each simulation step, the current_date is updated - its value can be seen in the top-left green info panel.
write "current_date at cycle " + cycle + " : " + current_date;
}
}
experiment main type: gui;
- Installation and Launching
- Workspace, Projects and Models
- Editing Models
- Running Experiments
- Running Headless
- Preferences
- Troubleshooting
- Introduction
- Manipulate basic Species
- Global Species
- Defining Advanced Species
- Defining GUI Experiment
- Exploring Models
- Optimizing Model Section
- Multi-Paradigm Modeling
- Manipulate OSM Data
- Diffusion
- Using Database
- Using FIPA ACL
- Using BDI with BEN
- Using Driving Skill
- Manipulate dates
- Manipulate lights
- Using comodel
- Save and restore Simulations
- Using network
- Headless mode
- Using Headless
- Writing Unit Tests
- Ensure model's reproducibility
- Going further with extensions
- Built-in Species
- Built-in Skills
- Built-in Architecture
- Statements
- Data Type
- File Type
- Expressions
- Exhaustive list of GAMA Keywords
- Installing the GIT version
- Developing Extensions
- Introduction to GAMA Java API
- Using GAMA flags
- Creating a release of GAMA
- Documentation generation