LAP-Related Work Packages

  • WP1 (Centres Setup) 1 PM
    WP2 (National Registry) 1 PM
    WP8 (LAP) 30.5+23 PM
    WP9 (Tool Adaptation) 0 PM
    WP10 (Metadata Adaptation) 2 PM
    WP11 (Management) 2.5 PM

Original Schedule

Compared to the proposed milestones from the project proposal, the project effectively started 18 months later than originally expected. The CLARINO grant was finally approved in the spring of 2012; the job search for the main LAP position completed in August that year, and LAP work effectively started in October 2012.

  • 8.1 LAP requirement and interface specification 2012 4 2013 3
    8.2 LAP first testable prototype 2013 1 2014 1
    8.3 LAP inclusion of analysis tools 2014 1 2014 3
    8.4 LAP first production version 2014 3 2015 1
    8.5 LAP documentation, workshop, evaluation 2015 2 2016 3
    8.6 LAP Tuning and complete version 2016 4 2017 3
    9.1 Tool adaptation, testable versions 2013 1 2014 3
    9.2 Tool testing and final versions 2014 2 2015 2

Revised Schedule

Due to repeated leaves of absence of core staff, LAP personnell allocation has lagged behind projections by close to nine person months at the end of 2014. Accordingly, the implementation of LAP milestones 8.2 and onwards have fallen behind schedule by a little more than half a year. With its progress report for the second tertial of 2014, the LAP team proposed the following schedule revisions:

  • 8.2 LAP first testable prototype 2013 1 2014 3
    8.3 LAP inclusion of analysis tools 2014 3 2015 1
    8.4 LAP first production version 2015 1 2015 3
    8.5 LAP documentation, workshop, evaluation 2015 4 2017 1
    8.6 LAP Tuning and complete version 2017 2 2018 1