Demand Response Component Implementation #72

@juflorez

Description

@juflorez

Minimal viable component:

  1. Documentation discussion/where to store examples information? Build off docstrings or start initial seed (Hari doc build out, all synced in one place) (julian add juflorez email to NREL organization)
  2. 100% payback (all energy shifted has to be returned in full, else it is counted as dropped load) or 0% energy loss hour to hour (some tradeoff between payback and energy loss).
  3. 4-hour window of allowable payback (otherwise counted as dropped load)
  4. Utilization of demand response occurs after storage (
    Create a min-cost flow problem for the multi-region max power delivery problem
    )

Component must abide by the following five constraints (from https://www.sciencedirect.com/science/article/pii/S0360544220303121#sec2.4)

(1) Dispatch power limitation: maximum power rating for reducing load from its baseline in each hourly timestep (assume static x value for now, could have time series varying)-charging limit
(2) Recovery power limitation: maximum recovery rating for increasing load from its baseline in each hourly timestep (can set percent of dispatch?-)-discharging limit
(3) Subdaily energy limitation: maximum energy availability over the specific subdaily period defining each end use (max length of DR event, min downtime) -energy capacitycccccbkrvgrrbilehekttrfurvggjitlnedckejerful
(4) Maximum number of DR events per day (can set static)
(5) Recovery schedule: the maximum allowable time that can pass before energy recovery from the initial DR event (effectively when loss of load happens)

Dispatch order process:
Generator
Transmission
Storage
Demand Response: need to calculate the available energy (load minus generation versus excess generation in the storage case)

Effectively a storage component with another parameter of allowable payback, instead of charging from excess generation, charging from excess load.

Key modules being changed:
PRASFILES modifications: parsing of new component/user inputs
PRASCORE modifications: MinCostFlows and need for additions? Addition of storage 2.0 component

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions